Our References
USA
Lay Hydropower Plant
1x Mix Flow Propeller
Project of Litostroj Group
Overhaul and modernisation of turbine and generator
Runner diameter – 175,6”
Maximum turbine output – 30,5MW
*Project under execution
USA
HPP City of Norway – Sturgeon Falls
Francis Horizontal Turbine
Project of Litostroj Group
Overhaul and modernisation of turbine and generator
Runner diameter – 70,1”
Rated turbine output – 740 kW/runner
Unit I (4 runners) and Unit II (2 runners)
*Finalised in 2019
Czech Republic
Dlouhé Stráně
Pumped-Storage Hydropower Plant
2 reversible Francis turbines
Project of Litostroj Engineering
Overhaul and modernisation of the largest reversible water turbine in Europe
Runner diameter – 4,540 mm
Output of a single turbine – 325 MW
Czech Republic
Dalešice
Pumped-Storage Hydropower Plant
4 reversible Francis turbines
Project of ČKD Blansko Engineering
Overhaul of three turbines
Runner diameter – 6,000 mm
Output of a single turbine – 112.5 MW
Czech Republic
Slapy
Hydropower Plant
3 Kaplan turbines
Project of ČKD Blansko Engineering
Overhaul and modernisation of a turbine
Runner diameter – 3,900 mm
Output of a single turbine – 55.4 MW
Czech Republic
Lipno
Hydropower Plant
2 Francis turbines
Project of ČKD Blansko Engineering
Overhaul and modernisation of a turbine
Runner diameter – 2,150 mm
Output of a single turbine – 67 MW
Georgia
Khrami GES 1
Hydropower Plant
2 Pelton turbines
Project of ČKD Blansko Engineering
Supply of a runner
Runner diameter – 2 520 mm
Output of a single turbine – 38 MW